About this document
How to read this document
The white paper makes the argument. This document holds the working underneath it: the tables, dates, rates and project figures the argument rests on, each tied to its published source, so that any reader, a ministry official, a PURC analyst, a journalist, can check a number without taking the paper’s word for it.
Three conventions apply throughout. First, Eastern Caribbean dollars are the primary currency, with US dollars converted at the fixed peg of EC$2.70 = US$1.00. Barbados figures are in Barbados dollars (BBD$2.00 = US$1.00) as published. Second, where credible sources disagree, both figures are shown and the disagreement is stated rather than resolved by preference; the installed solar stock in Section 1 is the clearest case. Third, anything the research could not verify from published sources is not estimated or filled in. It is listed in Section 8 as an open question, in the form a Grenadian official could answer directly.
The research was compiled on 18 October 2026. Sources are marked in the register in Section 9 as verified live where the document itself was opened and read, and index where only search-result text was available. Tenders described as in progress, the airport solar award and the battery tender closing 23 October 2026 among them, may have advanced since.
Section 1
Sector data
Grenada’s electricity system is small, single-utility and diesel-based: one licensee, Grenada Electricity Services Ltd (Grenlec), serving Grenada, Carriacou and Petite Martinique, with electrification above 99.5 percent. The tables below assemble what the published record says about its size, its fuel mix and its customers. The snapshots come from different years and different publishers, and they do not always agree; each row carries its source and date so the differences stay visible.
System snapshots
| Measure | NREL snapshot, c.2015 | CCREEE Report Card, 2020 | Grenlec Annual Report, 2020 | PURC tender filing, Nov 2024 |
|---|---|---|---|---|
| Peak demand | 30.2 MW | 32 MW | 31.86 MW | 37.67 MW |
| Base load | not stated | 20 MW | not stated | not stated |
| Installed capacity | 48.59 MW | 52.00 MW | 52.07 MW | 50 MW diesel (15 sets) |
| Generation / sales | 196.7 GWh generated | 202,460 MWh sold | not stated | not stated |
| System losses | 7.7% | 7.22% | not stated | 7.05% (Sep 2024, Grenlec filing) |
| Customers | not stated | not stated | more than 54,000 | not stated |
Sources: NREL Island Energy Snapshot, Grenada (c.2015); CCREEE, Grenada Energy Report Card 2020 (released January 2024); Grenlec Annual Report 2020; PURC tender background as reported by pv-magazine, 19 November 2024; Grenlec filing to the Eastern Caribbean Securities Regulatory Commission (ECSRC), September 2024, which also records fuel efficiency of 18.61 kWh per imperial gallon for the first nine months of 2024. Grenlec reported record monthly sales through the first half of 2024, up 15.21 percent year to date against 2023 before Hurricane Beryl. In 2025 Grenlec rented an additional 10 MW of temporary capacity and began procuring new engines; the World Bank has noted that many Grenlec units reach the end of their economic life within two to four years of February 2025.
Generation mix and installed capacity, 2024
Where Grenada’s electricity came from, 2024
Consumption by sector, c.2015
The installed solar stock: four published figures
How much solar Grenada already has depends on which publisher and which definition is used. All four figures below are in the published record; they differ by what they count (solar only or all renewables, utility or customer-owned) and by date. They are shown together because the white paper’s baseline, and any target set against it, depends on which one is adopted.
| Source | Figure | Capacity |
|---|---|---|
| IRENA statistics, via pv-magazine (January 2026) | Cumulative solar capacity, end of 2024, unchanged since 2020 | 4 MW |
| PURC tender background (November 2024) | Utility small-scale PV 1.1 MW plus customer-owned renewables 3.5 MW | 4.6 MW |
| NDC 3.0 (October 2025) | Solar PV operational by end of 2024 | about 6.2 MW |
| IRENA workshop reporting (November 2025) | Installed renewable capacity in 2024, of which 5.3 MW self-generation | about 6.4 MW |
Solar resource
Global horizontal irradiation exceeds 5 kWh per square metre per day; the National Energy Policy annex gives a range of 5 to 6 kWh per square metre per day. The one Grenadian project with a published yield projection, Limlair on Carriacou, works out to about 1,828 kWh per kWp per year (Section 6). IRENA’s SolarCity Simulator assessment of St George’s, Grand Anse, Grenville and Hillsborough in Carriacou found that 30 MW of rooftop PV in those four towns could meet 28.5 percent of Grenada’s electricity demand. No published audit of hotel, public-building or warehouse roof area was found beyond that four-town assessment, and no feeder-level hosting capacity study or map was found at all; both gaps are carried into Section 8.
Section 2
Tariff history and structure
A Grenadian electricity bill has three parts: a non-fuel charge fixed by customer class, a fuel charge that passes the cost of imported diesel through to customers, and government charges. The non-fuel charge has barely moved since 2016. Nearly all of the movement in what households and businesses actually pay comes from diesel.
Non-fuel charge by customer class
| Customer class | Non-fuel charge, EC$/kWh | US$/kWh |
|---|---|---|
| Domestic | 0.4057 | 0.150 |
| Commercial | 0.4375 | 0.162 |
| Industrial | 0.3207 | 0.119 |
| Street lighting | 0.3839 | 0.142 |
Source: Grenlec notice, 13 September 2022. These rates have been unchanged since 2016, apart from a temporary 25 percent reduction that ran from 5 January to 8 September 2022. Tariff reform remains unfinished: Grenlec submitted an Interim Tariff Methodology to PURC in 2022 and was still awaiting feedback in its 2022 reporting, and the legacy fuel and non-fuel structure remains in use.
The fuel charge
Grenlec treats fuel as a pass-through to customers. In its 2022 reporting the company described customers paying an average of the fuel price over the prior three months, which produces under-recovery when prices rise and over-recovery when they fall: under-recovery of EC$5.4 million in 2021, over-recovery of EC$1.65 million in 2022, and over-recovery of EC$16.15 million reported for the first half of 2024 alone. Grenlec was reviewing its Fuel Adjustment Clause to move to full monthly pass-through. Sampled fuel charge values from Grenlec’s own bill materials and filings:
| Period | Fuel charge, EC$/kWh | US$/kWh | Source |
|---|---|---|---|
| 2019, by month | 0.43 to 0.51 | 0.16 to 0.19 | Grenlec filings |
| 2020 average | about 0.32 | 0.12 | Grenlec filings |
| April 2023 (sample bill) | 0.61 | 0.23 | Grenlec bill brochure, August 2023 |
| February 2024 (sample bill) | about 0.646 | 0.24 | Grenlec bill flyer, February 2024 |
| June 2024 | 0.5550 | 0.21 | Grenlec ECSRC filing, June 2025 |
| June 2025 | 0.4829 | 0.18 | Grenlec ECSRC filing, June 2025 |
The realised average rate
Average realised electricity rate, EC$ per kWh
A worked domestic bill, February 2024
Government charges
Two government charges sit on top of the energy charges. The environmental levy is EC$5.00 for domestic customers using 100 to 150 kWh and EC$10.00 above 150 kWh, and is paid over to the Solid Waste Management Authority. VAT is charged at 7.5 percent on the non-fuel component only, with the first 99 kWh for domestic customers exempt. Renewable energy equipment imports carry a full waiver of duties and taxes, with only a 6 percent customs service charge applied, as stated in NDC 3.0.
A time-limited government relief package runs from August to December 2026: VAT zero-rated on the non-fuel component for all customers, a EC$50 credit for domestic customers using 1 to 200 kWh, and temporary removal of the 6 percent customs service charge on diesel imported for generation, which Grenlec describes as the only government tax on that diesel. The package says something about tariff politics in Grenada: headline rates can move quickly, and by decision rather than by formula.
What exported solar has been paid
No current PURC-published avoided-cost figure was found, and no published net-billing or net-metering export rate in force was located; the World Bank’s CEGEB project, approved in February 2025, lists developing net-billing guidelines for solar as work still to be done. The only Grenadian buy-back rate in the record is historical: in 2016 and 2017, customer renewable energy exported to the grid was paid at roughly EC$0.45 per kWh (about US$0.17), under either a historical-average fuel-cost option or a prior-year fuel-value option, against a retail price at the time of about EC$1.08 per kWh. In other words, exports were valued at fuel cost only, at well under half the price the same customer paid for imports. That fuel-only logic is the single most important tariff fact for distributed solar design, and whether it still governs is the first of the open questions in Section 8.
Section 3
Grenlec and PURC: a timeline
The present structure of the sector was set in three moves: the 1994 privatisation, which locked in a monopoly to 2073; the 2016 Acts, which opened the sector in law and triggered an arbitration that cost the state US$63 million to settle; and the slow build-out of the regulator since. The dates below are the spine of that story.
The self-generator caps in force, as stated in NDC 3.0, are the operative constraint on rooftop solar today: residential systems are limited to 120 percent of nominal daily electricity demand, and commercial systems to 60 percent. Both the caps and the wider framework are stated in NDC 3.0 to be under review.
Section 4
Project register
The pipeline is suddenly large relative to a 37.67 MW peak grid. The register below lists each project the research found, with its capacity, its status as published, and the figures attached to it. Where the sources leave a relationship between projects unclear, the register says so rather than guessing.
856 kWp of bifacial panels (1,450 modules at 590 Wp), battery storage revised to 400 kVA / 768 kWh, and a 750 kVA transformer, funded by a US$3.5 million grant from the UAE Caribbean Renewable Energy Fund (UAE-CREF, agreement 2019). Engineered to ASCE 7-10 for a 168 mph (75 m/s) basic wind speed, a Category 4 equivalent. Projected output before the storm: 1,565 MWh per year, saving more than 83,500 gallons (about 316,000 litres) of diesel a year, worth about US$38,000 a month, and offsetting 15 to 20 percent of Carriacou’s diesel generation.
Status: notice to proceed was given to the EPC contractor in December 2021 and completion was due in July 2024. The project was severely impacted by Hurricane Beryl, which made landfall on Carriacou on 1 July 2024, weeks before completion. No source found states the repair cost, the share of modules lost, or the rebuild contractor and timeline; see open question 8.
NDC 3.0 states that the government is pursuing reconstruction of an approximately 800 kWp solar plant in Carriacou damaged in the hurricane, with 400 kW of battery storage currently planned, alongside grid upgrades to carry more PV on the sister islands. CCRIF’s post-Beryl payout reporting also lists a “BESS Limlair Solar Farm” resilience allocation among the uses of Grenlec’s US$9.32 million payout. Whether the rebuild is complete as of October 2026 was not established; see open question 8.
Three ground-mounted solar plants at Maurice Bishop International Airport totalling 15.1 MWp, about 40 percent of system peak demand, with battery storage of 10.6 MW / 21.2 MWh, under a 25-year power purchase agreement for the winning independent power producer. PURC is the procurement entity and RMI the technical partner, under a memorandum signed 21 March 2025. Prequalification opened in December 2024 and a request for proposals was issued to qualified bidders in 2025; Grenlec is to build a new substation, lines and the battery integration. The stated purpose includes a resilient microgrid at the airport able to carry critical loads through long outages. Secondary reporting says World Bank financing of US$18.5 million for the battery and transmission package was negotiated in 2024; that figure was not confirmed on a World Bank page in this research, and the tender outcome and PPA price were not published in the sources found.
A separate Grenlec tender for 5.5 MW / 11 MWh of battery storage, valued at about US$8.7 million, with bids due 23 October 2026. The financing package behind it is a US$3 million grant from the UK Foreign, Commonwealth and Development Office and the European Union, plus a US$5.7 million loan from Canada under the SuRGE (Supporting Resilient Green Energy) programme, both through the Caribbean Development Bank, with World Bank parallel financing for a compatible battery.
Unresolved: whether this 5.5 MW / 11 MWh unit is part of, overlaps with, or is additional to the airport project’s 10.6 MW / 21.2 MWh battery is not clarified in any source found. See open question 9.
PURC’s distributed generation procurement. The pilot launched in 2021 for facilities of 30 to 200 kW; licensees sign PPAs with Grenlec. The pilot grant reported in 2024 licensed eight investors; NDC 3.0 states the 2021 request for proposals resulted in nine IPPs totalling 850 kW. A second call closed 10 October 2024, and NDC 3.0 records that in 2025 a combined total of 5 MW is being sought in a similar call. PURC’s chief executive has said of the pilot that it “took quite a while because we had to develop a rigorous regulatory framework”; the pilot produced roughly 850 kW of licensed capacity in about three years, which is the delivery pace the white paper’s design is built to change.
A household and small agro-processor program of the Ministry of Climate Resilience, Environment and Renewable Energy, officially launched in November 2025, with a focus on vulnerable and energy-insecure households. Systems are 1 to 6 kW, grid-tied, off-grid or hybrid; the installer scope covers site assessment, design, mounting, commissioning and handover. An expression of interest for qualified installation firms closed on 30 January 2026. It is the first official Grenadian solar program aimed at agro-processors as well as households.
The Caribbean Efficient and Green-Energy Buildings Project, approved by the World Bank Board on 28 February 2025, is a US$131.87 million regional program covering Grenada, Guyana and St Lucia plus the OECS Commission and CCREEE. Grenada’s share is US$40 million of IDA financing plus a US$8.5 million Clean Technology Fund loan. The program retrofits about 500 public buildings across the region for at least a 20 percent cut in energy consumption, adds rooftop solar, and funds regulatory work including net-billing guidelines. NDC 3.0 states the project is expected to add an estimated over 8 MW of rooftop solar PV in Grenada. Implementation agreements between the government and Grenlec were reported signed on 15 August 2025.
Caution: NDC 3.0 pairs the 8 MW figure with battery storage of 10.6 MW / 21.2 MWh, which matches the airport project exactly; the attribution may conflate the two projects and the 8 MW should be treated as an estimate pending project documents.
The pre-pipeline stock was built site by site, because, in Grenlec’s words, securing suitable land is difficult on a mountainous island: a 31.6 kW ground-mounted array on Petite Martinique (2013) meeting about 20 percent of that island’s peak, a 13.9 kW rooftop system at St Andrew Anglican Secondary School (2014), a 10 kW system at Maca Bana Villas (2009), and rooftop systems at Grenlec’s own Grand Anse offices. Grenlec and its customers together operated 2.36 MWp at the time of the company’s renewables page (undated, about 2020).
NDC 3.0 lists two 1 MW floating solar projects on irrigation ponds and a 2 MW wave energy project as under conceptual development. A 2 MW wave project under a Seabased memorandum is reported in secondary sources. None is operational in the sources found.
Hurricane Beryl: the stress test the register has to answer
Beryl made Category 4 landfall on Carriacou on 1 July 2024. The Post-Disaster Needs Assessment (Government of Grenada and UNDP, March 2025) put total effects at EC$595.16 million, 16.74 percent of 2023 GDP, with 40,600 people affected, 39 percent of the population. Two other official figures circulate and are not the same measure: the IMF’s January 2025 Article IV put damage at about 16 percent of GDP, and the World Bank’s country page cites a GRADE assessment of US$218 million in damages; the Prime Minister’s early estimate of roughly a third of annual output was superseded by both. Energy-sector damage was US$4.77 million with losses of US$2.56 million. Grenlec had 19,318 customers offline: 15,307 on the mainland (25 percent) and 4,011 in Carriacou and Petite Martinique (100 percent). Ninety-seven percent of mainland customers were restored by the end of the first week; full restoration took until the end of October 2024, with CARILEC mutual-assistance crews from six regional utilities. Grenlec’s CCRIF parametric payout was US$9,323,275 (EC$25.1 million), paid within 14 days; government CCRIF payouts across its policies totalled US$44 million. Part of Grenlec’s payout funds undergrounding the St George’s West feeder serving the General Hospital and the Carriacou West feeder serving the desalination plant.
Section 5
Caribbean peer programs
Grenada is not choosing in the abstract. Four neighbours have already run the experiments that matter: a published feed-in tariff in Barbados, utility tenders in Jamaica, a utility-owned first plant and simple net metering in St Lucia, and publicly de-risked geothermal in Dominica. The regional floor is set by the OECS roadmap. The detail below is what the white paper’s benchmarking rests on.
Barbados: the feed-in tariff
Barbados runs the region’s most developed distributed solar market, built on the Renewable Energy Rider and then a feed-in tariff (FIT) programme administered by the Fair Trading Commission (FTC): fixed tariffs for 20 years, set from the cost of generation, differentiated by system size, allocated first come, first served. Before the FIT, the Rider paid BBD$0.416 per kWh for solar. Systems at or below 3 kW operate on sale of excess only; larger systems on buy all, sell all. Community-shared projects, with at least 15 residential investors and no single owner above 50 percent, received a 10 percent premium in the first round, and Rider customers were grandfathered for 20 years.
| Solar size band | 2019 to 2021 round, BBD cents/kWh | 2023 round, BBD cents/kWh | 2023 round, US cents/kWh |
|---|---|---|---|
| Up to 10 kW | 42.75 | 34.25 | 17.1 |
| Over 10 to 100 kW | not extracted | 35.75 | 17.9 |
| Over 100 to 250 kW | not extracted | 34.75 | 17.4 |
| Over 250 to 500 kW | not extracted | 39.75 | 19.9 |
| Over 500 kW to 1 MW | 36.25 | 34.25 | 17.1 |
Sources: Barbados FTC feed-in tariff decisions. The 2023 round allocated 27.6 MW to solar out of 32.6 MW across all technologies. US cent figures are converted at the Barbados peg of BBD$2.00 = US$1.00. Per-band rates for the middle bands of the 2019 to 2021 round were not extracted in this research; only the endpoints of the published range, BBD$0.3425 to 0.3975 per kWh across the programme, are stated in the text.
Barbados 2023 feed-in tariff by size band
What the tariff built by December 2020
The comparison that matters for Grenada is proportional. Barbados reached 39 MW of distributed PV on a grid of roughly 135 MW peak. Scaled to Grenada’s 37.67 MW peak, the same penetration is about 10 MW of rooftop and small commercial solar, roughly twelve times what the SSIPP pilot licensed in its first three years. Barbados has since run into grid-absorption and licensing constraints at higher penetrations, widely reported regionally; those reports were not verified against a primary FTC source in this research, and the lesson cuts both ways: a published tariff works, and the grid rules have to be ready for what it brings.
Jamaica: scale by tender
Jamaica had 188 MW of renewable capacity by December 2024, about 10 percent of generation, up from 7 percent in 2016 (solar 3.05 percent and wind 5.89 percent of generation in 2024). Its target is 50 percent renewable generation by 2030. About 100 MW of solar was awarded in November 2024 and further utility tenders in the 300 MW class are in preparation. Net billing and wheeling frameworks exist under the Office of Utilities Regulation, though the rate detail was not verified in this research. The Jamaican path is the inverse of Barbados: capacity arrives through competitive utility tenders, and household rooftop plays a secondary role.
St Lucia: utility first, then a simple window
St Lucia’s first utility-scale renewable plant was the 3 MW La Tourney solar farm (2018, EC$20 million, owned by LUCELEC), generating about 7 GWh a year. Small-scale integration runs through net metering for residential systems of 5 to 25 kW; a residential customer using 800 kWh a month paid about US$0.337 per kWh in the April 2026 sector snapshot. The next step is a tender for 10 MW of solar with 13 MW (about 26 MWh, two-hour) of battery storage, with bids due in January 2026 on secondary reporting. St Lucia is Grenada’s partner in both CEGEB and the regional finance facility below.
Dominica: the geothermal template
Dominica’s 10 MW geothermal plant in the Roseau Valley (Laudat) is the working model for the path Grenada is on. The state de-risked the drilling with concessional finance from the CDB, the Green Climate Fund and the World Bank, then signed a 25-year build-own-operate power purchase agreement with Ormat at COP28 in 2023, with transfer at term. Construction began in June 2024, was about 90 percent complete in August 2025, and commissioning was scheduled from December 2025 with commercial operations targeted for March 2026; a new high-voltage line to Fond Cole (US$1.88 million from an existing World Bank loan) connects it. Dominica’s goal is about 100 percent renewable electricity by 2030. The sequencing is the lesson: roughly fifteen years separate Dominica’s early drilling from its plant, which is why Section 7 treats Grenada’s geothermal as a 2030s resource and solar plus storage as the resource that can move this decade.
The OECS floor
The OECS Sustainable Energy Roadmap 2025 to 2035 and the Basseterre Declaration, adopted at the third Council of Ministers: Energy meeting in St Kitts on 4 to 5 February 2025, set 30 percent renewable penetration across the OECS by 2030, with a minimum of 20 percent in each member state, and 50 percent by 2035. Grenada’s minister, Kerryne James, was the outgoing chair of the Council. Regional context from the same process: OECS tariffs run from EC$0.41 to EC$1.08 per kWh, and diesel accounts for 75 percent to nearly 100 percent of installed capacity in some member states. Grenada’s own commitments sit inside that frame: NDC 3.0 holds the economy-wide target at 40 percent below 2010 emissions by 2030, maintained or deepened to 2035 and conditional on international support, prices the whole transition at over US$2 billion, and commits Carriacou and Petite Martinique to 100 percent renewable electricity.
Section 6
Diesel displacement economics
Every figure in this section is built from one local anchor: the Limlair project on Carriacou, whose published projection was 1,565 MWh a year from 856 kWp, a yield of about 1,828 kWh per kWp per year (a capacity factor of about 21 percent), saving more than 83,500 gallons of diesel a year. Because it is a Grenadian project on a Grenadian island, its yield already reflects local cloud, temperature and system losses in a way an imported modelling figure would not.
The anchor, scaled
| Unit of solar | Generation per year | Diesel displaced, Limlair ratio | Diesel displaced, fleet efficiency |
|---|---|---|---|
| 1 kWp (a few panels) | 1,828 kWh | about 369 litres | about 447 litres |
| 1 MWp | 1,828 MWh | about 369,000 litres (97,500 US gal) | about 447,000 litres |
| 10 MWp | 18,280 MWh | about 3.69 million litres | about 4.47 million litres |
How the two diesel columns are derived. Limlair ratio: the project’s stated saving of about 316,081 litres a year divided by its 856 kWp, or 369 litres per kWp per year. Fleet efficiency: Grenlec reported fuel efficiency of 18.61 kWh per imperial gallon for the first nine months of 2024; 1,828 MWh at that rate needs about 98,200 imperial gallons, or about 447,000 litres, per MWp. The range between the columns is real: which diesel a solar kilowatt-hour displaces depends on which generating set is backed off, and small island sets on Carriacou differ from the Queen’s Park fleet. Both bounds are from Grenadian sources; no imported conversion factor is used.
Diesel displaced each year, litres (Limlair ratio)
Value of 1 MWp of generation, per year
Fuel spend and foreign exchange context
PURC’s chief executive stated in 2024 that “over one hundred and fifty million dollars are spent on fuel for these generators annually”; the report of that statement does not specify whether the figure is EC or US dollars, and at EC$150 million it would be about US$55.6 million a year. A commercial source cites about 47.9 million litres of imported diesel a year for electricity alone, undated. On that import figure, 10 MWp of solar at the Limlair ratio displaces roughly 7.7 percent of the diesel imported for generation, and generates about 9 percent of the electricity Grenlec sold in 2020 (18,280 MWh against sales of 202,460 MWh). Every litre displaced is a litre that does not have to be bought in foreign currency: across the Eastern Caribbean, fossil fuel imports averaged US$444 million a year from 2016 to 2021, 15.4 percent of total imports, on World Bank figures. That regional figure is context, not a Grenadian statistic; no Grenada-specific series for the electricity fuel import bill was found (open question 7).
Two cautions belong with this arithmetic. First, Grenlec’s fuel recovery swings, from EC$5.4 million of under-recovery in 2021 to EC$16.15 million of over-recovery in half of 2024, mean the avoided cost in any given year moves with the oil price and the averaging window; a program priced off a single year’s fuel charge will be wrong in both directions over its life. Second, displacement is not the same as bill savings for the utility unless the export price is set below the avoided fuel cost, which is exactly the design question the white paper addresses. What the arithmetic does establish is scale: on Grenada’s small grid, single-digit megawatts of distributed solar are not marginal. Ten megawatts is a measurable share of national fuel imports.
Section 7
Geothermal briefing
Geothermal is Grenada’s baseload bet, and the white paper treats solar plus storage as its complement rather than its substitute. This briefing records where the Mt St Catherine project stands, what money is behind it, and the timeline the published record supports.
Prospects near Mt St Catherine, with Plaisance in St John and Tricolar in St Patrick named in earlier plans. Surface studies support a plant of 15 MW, which the Caribbean Development Bank (CDB) states could displace about 55 percent of total electricity generation from diesel. An older NREL assessment put Grenada’s geothermal potential above 50 MW, alongside solar potential of 25 to 50 MW and wind of 20 MW; those are resource estimates, not project figures.
The CDB approved US$9.4 million in 2023 for the Geothermal Drilling Project, with the Inter-American Development Bank, the Global Environment Facility, the European Union and Italy among the partners. The United Kingdom’s Foreign, Commonwealth and Development Office pledged £10 million in early 2024, formalised by memorandum in 2025. The New Zealand government provides technical support.
The original design was two exploratory slim wells. UK funding expands the campaign to deeper, wider rotary wells with directional drilling in place of slim holes. Preparatory work is complete: the environmental and social impact assessment, land acquisition, and a dedicated Project Management Unit are in place, and engineering and procurement are advanced.
The project timeline has been extended to 2028. If drilling results are favourable, a competitive tender will seek private investment to build and operate the plant. NDC 3.0 states that a 15 MW geothermal plant could be in operation within the next decade. On the Dominica comparison in Section 5, where the same sequence took roughly fifteen years from drilling to operation, a Grenadian plant is an early-2030s prospect at best, which is why the near-final IRRP plans solar plus storage as the complement that carries this decade. Wind, for completeness, is modelled in two IRRP scenarios with preliminary data described as promising, but NDC 3.0 flags hurricane resilience of wind infrastructure as an unresolved concern; no operating utility wind farm was found, and the 1 to 2 MW Carriacou wind project financed in 2012 (EU grant of €2.5 million plus €1.4 million from Grenlec) has no evidence of having been built in the sources found.
Section 8
Open questions register
The research behind the white paper was thorough and still could not verify the items below from published sources. They are set out plainly, as questions, because each one is answerable by a Grenadian official, regulator or utility officer, and several of them, the current export price above all, are load-bearing for program design. Nothing in the white paper rests on an assumed answer to any of them.
What are Grenlec’s exact current shareholding percentages? Aggregating the December 2020 settlement release gives the state about 61.6 percent (the 50 percent repurchased plus the 11.6 percent affiliate stake), but the release states no combined figure, the National Insurance Scheme and public holdings on record are pre-buyback, and the outcome of the strategic-partner process announced in July 2022 is not published in any source found.
Is the Integrated Resource and Resilience Plan final, and will it be published? NDC 3.0 says it was nearing finalisation in 2025. No final IRRP, PURC strategic plan, or feeder-level hosting capacity study was located.
What avoided cost of generation, in EC$ per kWh, does PURC currently recognise, and at what prices have SSIPP power purchase agreements actually been contracted? The only buy-back rate in the published record is the historical fuel-only figure of about EC$0.45 per kWh from 2016 to 2017.
Is net metering or net billing in force for self-generators today, under a published tariff order? Sources conflict in wording: IRENA workshop material describes PURC-led net metering, while the World Bank’s CEGEB project treats net-billing guidelines as work still to be developed. No PURC net-billing tariff order was located.
What is the shape of Grenada’s daily load: the peak hour, the split between daytime and evening demand, the air-conditioning share, and the tourism seasonality? No Grenlec load research or PURC filing answering these was found; the NDC 3.0 Cooling Roadmap, which targets cuts of 72 percent in household and 81 percent in commercial building electricity use against 2017, is the only official pointer to cooling as the swing load.
What are the current peak demand and installed capacity for Carriacou and Petite Martinique separately? Only dated figures exist in the record: 3.2 MW and 0.5 MW installed in 2011, and a Carriacou peak of about 1.3 MW in 2016. Grenlec does not publish island-disaggregated current figures in the sources found, and the sister islands’ 100 percent renewable commitment cannot be sized without them.
What is Grenada’s annual fuel import bill for electricity generation, as a share of imports or GDP? The available data points are PURC’s “over $150 million” statement, with the currency unspecified in the report of it, and a commercial figure of about 47.9 million litres a year. No IMF or central bank Grenada-only series was located.
What did Hurricane Beryl do to Limlair specifically: the repair cost, the share of modules lost, the rebuild contractor and timeline? NDC 3.0 records a planned rebuild of about 800 kWp with 400 kW of battery storage, but whether the rebuilt plant is complete as of October 2026 is not established in any source found.
Are the CDB-financed 5.5 MW / 11 MWh battery and the airport project’s 10.6 MW / 21.2 MWh battery the same unit, overlapping, or additional to each other? And what is the status of the airport IPP tender: the winning bidder and the contracted PPA price? The last confirmed status of the tender in the sources is the request-for-proposals stage.
What does property or all-risk insurance for private rooftop solar cost in Grenada, and on what hurricane terms? Only utility-level cover is documented: Grenlec’s CCRIF parametric policy for transmission and distribution. The household and commercial insurance market for rooftop systems is not priced in any source found.
What are the quantified electricity loads of the nutmeg and cocoa processors, the rum distilleries, the fisheries cold chain, and the hotel sector on its own? No published audit of any of them was found, nor any agrivoltaics pilot or study in Grenada; the commercial-small consumption block of 49.23 percent (c.2015) is the closest available figure, and agriculture’s exposure is documented only through Beryl, where farm losses of US$29 million were 62 percent of all losses nationally.
How many licensed electricians and certified solar installers does Grenada have, and which institution ran the Caribbean Vocational Qualification solar cohort that CCREEE’s 2020 Report Card records as 26 enrolled and 17 graduated? No census of installers was found, TAMCC’s listed programs include electrical installation but no dedicated solar PV qualification, and the institution’s name is garbled in the Report Card’s text.
What is the full text and legal status of the National Energy Policy 2023 to 2035, and of the reported target of 100 percent renewable electricity by 2035? The update is known through a secondary compilation of CCREEE’s 2023 Energy Report Card; the Grenada page was not individually extracted in this research.
What has happened in Barbados since the 2023 feed-in tariff round: round outcomes, and the reported grid-absorption curtailment and licensing pauses? The same question applies to current net-billing rates in Jamaica and St Lucia. The peer detail in Section 5 rests on the dated documents cited there, and a follow-up pass on primary FTC Barbados and OUR Jamaica decisions is recommended before peer rates are cited as current.
What is the Global Solar Atlas PVOUT figure for Grenada, in kWh per kWp, from the World Bank and Solargis country factsheet? The factsheet itself was not retrieved in this research; the yield figures used here rest on the Limlair project projection and the published irradiation range instead.
Section 9
Source register
All sources were read or searched on 18 October 2026. Each entry is marked verified live where the document itself was opened and read during the research, or index where only search-result text was available. Where sources disagree, Sections 1 and 4 give both figures.
Primary and official
- Verified liveGovernment of Grenada, Ministry of Climate Resilience, Grenada’s Third Nationally Determined Contribution (NDC 3.0), October 2025. climateresilience.gov.gd
- Verified liveMinistry of Climate Resilience portal, Limlair Solar PV Hybrid Project, Carriacou. climateresilience.gov.gd
- Verified liveCCREEE, Grenada Energy Report Card 2020 (January 2024 release). cekh.ccreee.org
- Verified liveWorld Bank, Caribbean Efficient and Green-Energy Buildings Project approval release, 28 February 2025. worldbank.org
- IndexGovernment Information Service, Grenlec share repurchase release, 29 December 2020. ecseonline.com
- IndexPublic Utilities Regulatory Commission, Draft Supply Code (posted March 2026, still draft). purc.gd
- IndexPublic Utilities Regulatory Commission, Tariff Setting Methodology, responses to comments. purc.gd
- IndexElectricity Supply Act No. 19 of 2016; PURC Act No. 20 of 2016; PURC (Amendment) Act No. 2 of 2025, legislative records via InforMEA. informea.org · informea.org · informea.org
- IndexGrenlec, non-fuel rate notice, 13 September 2022. grenlec.com
- IndexGrenlec, How Your Domestic Bill is Calculated, flyer, February 2024. grenlec.com
- IndexGrenlec, Understanding Your New Bill, brochure, August 2023. grenlec.com
- IndexGrenlec, government relief factsheet, 2026. grenlec.com
- IndexGrenlec, 2024 Year in Review (Beryl restoration). grenlec.com
- IndexGrenlec, CCRIF payout release. grenlec.com
- IndexGrenlec, PURC and RMI memorandum release, March 2025. grenlec.com
- IndexGrenlec, Annual Report 2020. grenlec.com
- IndexGrenlec filings to the ECSRC: 2022 annual reporting; June and September 2024; June 2025. ecsrc.com · ecseonline.com
- IndexEnvironmental and Social Impact Assessment, MBIA Solar PV, BESS and Transmission Project. climateresilience.gov.gd
- IndexCEGEB Environmental and Social Management Framework, October 2025. climateresilience.gov.gd
- IndexGovernment of Grenada and UNDP, Post-Disaster Needs Assessment, Hurricane Beryl, March 2025. undp.org
- IndexCCRIF SPC, Grenlec payout release and post-Beryl payout-use synopsis. ccrif.org · ccrif.org
- IndexInternational Monetary Fund, Grenada 2024 Article IV Consultation, January 2025. imf.org
- IndexCaribbean Development Bank, geothermal board paper and 2025 geothermal and battery releases. caribank.org · caribank.org
- IndexWorld Bank, Regional Renewable Energy and Infrastructure Investment Facility release, 17 April 2025. worldbank.org
- IndexWorld Bank, Development Policy Credit release, July 2023. worldbank.org
- IndexGreen Climate Fund, G-CREWS project page. greenclimate.fund
- IndexOECS Commission, Sustainable Energy Roadmap 2025 to 2035 and Basseterre Declaration releases, February 2025. pressroom.oecs.int · pressroom.oecs.int
- IndexBarbados Fair Trading Commission, feed-in tariff decisions; Government of Barbados, Ministerial Statement on renewable energy, December 2020. ftc.gov.bb · internationalbusiness.gov.bb · barbados parliamentary papers
- IndexT.A. Marryshow Community College, programme listings. tamcc.edu.gd · tamcc.edu.gd
Secondary and regional reporting
- Indexpv-magazine: Grenada launches 15.1 MW utility-scale PV tender, 19 November 2024; Grenada seeks installers for Solar for All program, 22 January 2026. pv-magazine.com · pv-magazine.com
- IndexCaribbean Times / Caribbean Media Corporation, PURC grants licences to Small-Scale Independent Power Producers. caribbeantimes.com
- IndexThinkGeoEnergy: Grenada geothermal funding and drilling preparation, 2025; Dominica plant commissioning. thinkgeoenergy.com · thinkgeoenergy.com
- IndexReuters, via Claims Journal, Grenada first to activate hurricane clause, 20 August 2024. claimsjournal.com
- IndexIMI Daily, compilation of Investment Migration Agency data on the Citizenship by Investment programme, 2024 to 2025. Gross programme revenue includes amounts due to approved-project developers; the government share is smaller. imidaily.com
- IndexGlobal Energy Monitor, country energy profiles: Grenada, Barbados, Jamaica. gem.wiki
- IndexNREL, Island Energy Snapshot: Grenada. nrel.gov
- IndexGIZ, Reform of the Electricity Sector to Support Climate Policy in Grenada. giz.de
- IndexJamaica Information Service, progress toward the 50 percent renewable energy target. jis.gov.jm
- IndexRMI, Saint Lucia Solar Park Opens, 2018. rmi.org
- IndexBusiness Grenada, Issue 7, 2016 to 2017: interconnection buy-back rates and Carriacou peak. joomag.com
- IndexCommonwealth Secretariat, Mobilising climate finance for NDCs: lessons from Grenada’s resource mobilisation strategy. thecommonwealth.org
Research compiled 18 October 2026 from the sources above. Figures are as published by their sources on that date; programs and tenders described as in progress may have advanced since, and the open questions in Section 8 stand until a source above, or the responsible Grenadian institution, answers them.